Settles officials aim for October opening

September 3, 2012

It has cost more and taken longer than anyone anticipated, but once renovation of the Settles Hotel is complete, officials said people are going to be wowed by what they see.

Renovation for the historic Big Spring landmark, which was built in 1930, will end up costing almost 100 times its original construction price tag of $500,000, officials said.

“As of (Thursday), we've passed the $30 million mark (on renovation costs), and we still have a ways to go,” said Project Director Bill Cole.

Police blotter

September 3, 2012

The Big Spring Police Department reported the following activity between 9 a.m. Saturday and 7 a.m. today:
• JOSEPH YANEZ, 40, of 1408 Oriole, was arrested Sunday on a charge of driving while intoxicated.
• IRMA MORIN YANEZ, 39, of 1408 Oriole, was arrested Sunday on a charge of public intoxication.
• OSCAR CANALES, 55, of 1700 S. Main, was arrested Sunday on warrants for failure to maintain financial responsibility, expired driver's license, expired motor vehicle inspection certificate, accumulated items/weeds/rubbish (two counts) and failure to appear.

Big Spring’s Canyon Atkinson, a seventh grade student and son of Shannon and Belinda Crenshaw, has...
Few things get me as pumped up about the upcoming football season as the day I receive my copy of...
Howard College's baseball program has a history of sending players off to the next level. Whether...
Mr. and Mrs. W.P. “Bill” Criswell will celebrate their 60th wedding anniversary June 19, 2013. Bill and Carol Willene...
Charlene Janell Stanley, daughter of A.J. and Sherrie Stanley, was the 2009 valedictorian of Forsan High School....

 

Premium Drupal Themes by Adaptivethemes